New Line · Bihar

Bihar – Sanctioned Railway Project Portfolio

Ongoing SOURCE VERIFIEDSource date: 2026-07-24

Route / geography

Statewide portfolio

Project position

Aggregate portfolio of new lines, gauge conversion and doubling works falling fully/partly in Bihar.

Current public status

As of 1 Apr 2026, 59 projects were reported: 32 new lines, 1 gauge conversion and 26 doubling works.

Key facts

●

59 projects

●

5,067 km

●

₹96,651 crore sanctioned cost

●

32 new lines

●

1 gauge conversion

●

26 doubling